Benton - Fist Floor Walls

The first floor walls are up.  We will be starting the second floor deck this week.

Benton - Deck

Here is the carpenter progress over the past few days on the deck. They are starting first floor walls today.  They even got out there on Saturday to try and make up for some lost time with the rain.

Benton - Rough Grading & Steel

After the driveway was roughed in we were able to get the truck in to set the steel.  Carpenters start with the deck in the morning.

Benton - Foundation

Here we are laying the utility sleeves.  The foundation has been mostly backfilled except an area for the sewer and water.  The steel will be set tomorrow if the weather cooperates.

Benton - Demo

Here's a few more photos of the demolition progress.  We have the village demo inspection tomorrow morning.  Then we'll be moving on to the excavation & starting the footings at the end of the week.

Bothwell - Tile, Flooring, Exterior

The outside is looking good.  Check out the bead board under the front porch.  Though, we'll get a much better view once the scaffolding comes out of the way.  The tile in the baths and laundry was just finished today.  The first floor will be entirely oak and will be finished up this week.

Benton - Demolition

Here it is.  The old house coming down.  It's a great rainy day for it too.  The rain helps keep the dust down.

239 S Benton - Sewer & Water

Sewer and water main disconnects and stub connections.  We disconnect and reconnect at the same time so the street is only opened up once.  The stubs in the parkway will be ready to go once the foundation is poured.