Stone Garden
215 N Brockway, Palatine - Finished Home
Here are some final interior photos.
221 Brockway
We are waiting on pouring the basement concrete before we can continue on this one. Weather has been too cold the past few weeks.
215 Brockway
Here are a few progress photos of this project. We are getting there...
215 N Brockway - 1st Floor Rough Framing
We stared building Lot 4 of Stone Garden. If everything works out we should be able to get this house all sealed up before the winter.
225 Brockway
Lot 2 in Stone Garden Subdivision is finished. We'll be using this home as the model. On the exterior we still need the final grading and to install the gutters, but otherwise this home is ready for move-in.
229 Brockway
Lot 1 in Stone Garden Subdivision is moving along on schedule. We just passed the rough inspections and we're gearing up for insulation and drywall after the 4th of July Holiday.
225 - Rough
The first house in our 5 home subdivision, Stone Garden, is scheduled for rough inspections in a couple days. Here are some photos of the progress.