Home Progress

Bothwell - Primed and Stairs

Figured it was about time for some updated photos of Bothwell.  The weather has been brutal this year; really slowing us up.   The masons were able to start last week, but then temperatures dropped again so we have to wait.   The new pictures show the stairs by Designed Stairs, and the freshly primed walls.

Bothwell - After Drywall

Bothwell is moving along.  Though due the the extreme temperatures we have been having it has been moving slowly.  The house is ready for priming, but the garage is still too cold to hang drywall.

Bothwell - Rough

Rough Plumbing, Mechanicals, Electric, and Framing completed. After we pass inspections insulation begins. Then we can finally heat the place up.

248 S Hale - Finished

This home is just about finished.  Only a few quick miscellaneous items remain.  Here's a look at the finished product.

111 S Bothwell - Raising Walls

The first floor deck is on.  We helped raise the back wall today.  Hopefully Com Ed will hook up the electric soon so we can get off the generators. 

111 S Bothwell - Foundation

The foundation is up.  

Once the small strips of Styrofoam are removed you'll see a small brick ledge that allows us to go lower with the bricks.  This is a nice detail as is hides much of the concrete foundation on the finished home.