Rough plumbing is finished and we’re starting the hvac and fireplace install.
947 N Haddow
Rough plumbing is finished and we’re starting the hvac and fireplace install.
Rough plumbing is finished and we’re starting the hvac and fireplace install.
Siding is being finished and on the interior the drywall was just hung.
Had a professional take some photos.
The rough framing and roof trusses are finished. Next up is to install the windows.
Here we have the final rough grades, but we still need the top soil, landscaping, and driveway asphalt.
Here we are starting another new home in Arlington Heights. Excavation is done and the foundation was poured. We’re just about to remove the forms and prep for backfill.
We started another home in Palatine. Foundation and backfill are complete. Here we set the steel and added gravel for the garage and construction drive. Carpenters are up next.
Most the siding and all the stone work is complete. We need to finish the front porch siding after we pour the concrete later this week.
The home is insulated and ready for drywall. Full masonry fireplace is up, but it still needs mantle and hearth installed.