1850 Hamilton

1850 Hamilton Ct - Finished Photos

Here's some photos of the finished home.

Hamilton - Tile & Stairs

Tile prep work has begun over at 1850 Hamilton.  The tile flooring in the laundry room and 2nd floor furnace room have been installed.  Custom oak stairs have been installed.  The iron balusters will be put into place after painting and staining.

Hamilton- Insulation

1850 is Insulated.  Drywall to being next week.  I am very excited to get moving again on this home.  There will be tons of great pictures coming up with all the decorative trim details going in.  While we're waiting for the good stuff, here's some pictures of insulation & drywall setup.

Hamilton - Rough

Exterior is closing up and coming together.  The Electrician is starting work and we should be ready for the rough inspections in a few weeks.

Hamilton - Framing Progress

The basement is poured, most of the windows are in.  We are still working on getting this house closed up.  The next steps will be to the frame out the basement walls and get the plumber started.  On the exterior we will need the window trim installed so we can start the stone.

Hamilton - 1st Floor Framing

The carpenters are finished with the first floor.  The next step is to have the steel put up.

1850 Hamilton - Foundation

Here are some shots of 1850 Hamilton just before and after the foundation forms were put up.  We just passed the inspection today and the walls will be poured tomorrow.  Now that the weather is cooperating we should really be able to get moving on this home.