April Home Progress

We are finishing the rough framing at 134. Siding at 156. And just poured the concrete for the garage & stoops at 2300.

Home Updates

2300 is almost finished with the rough mechanicals and we are working on the masonry. 156 we are hanging Drywall. 134 we are rough framing and just getting to the 2nd floor deck.

2300 & 156

2300 Brockway, our concrete contractor is pouring the basement slab now that the temperature has warmed up enough.

156 W Aldridge, rough plumbing & HVAC are complete. The electrician has started on the 2nd floor now.

Home Progress

156 W Aldridge is framed with roof shingles & windows installed. The basement slab was just poured and will need a few days to cure before we can continue.

The carpenters are still framing 2300 Brockway. We are hoping the weather holds out for us to get the roof shingles on without any delays.

Both projects are a little further along than the photos, but this was a nice bright to show some progress.