Here we have the final rough grades, but we still need the top soil, landscaping, and driveway asphalt.
Home Progress
947 N Haddow - Foundation
Here we are starting another new home in Arlington Heights. Excavation is done and the foundation was poured. We’re just about to remove the forms and prep for backfill.
649 S Oak - Steel & Gravel
We started another home in Palatine. Foundation and backfill are complete. Here we set the steel and added gravel for the garage and construction drive. Carpenters are up next.
5N773 Rochefort
Most the siding and all the stone work is complete. We need to finish the front porch siding after we pour the concrete later this week.
5N773 Rochefort - Insulation
The home is insulated and ready for drywall. Full masonry fireplace is up, but it still needs mantle and hearth installed.
5N773 Rochefort - The Rough
We have all the rough mechanicals installed including framing, fire stop, plumbing, HVAC, and electrical. The masonry and fireplace is just about complete. The well & septic were installed too. We are ready for the Village rough inspections, then moving on to insulation and drywall.
5N773 Rochefort - Concrete
Rough framing & roofing are done. We just poured the concrete slabs. Next we’ll frame the basement and start the mechanicals.
Roof & 2nd Floor Framing
For the most part the weather has been very good for building this winter. Here the carpenters have framed the 2nd floor and are setting roof trusses.
5N773 Rochefort - Framing
We have the 2nd floor steel installed and are continuing with the rough framing.
5N773 Rochefort - Kneewall & Steel
Here we have the foundation finshed & backfilled with the kneewall almost complete. Our steel contractor is working with our carpenters to set the steel.