Here are a couple of shots of the mostly finished exterior. The home still needs painting on the columns & front door, and landscaping.
Home Progress
Michigan - Rough
We're finishing up the rough electrical and then we'll be ready to start insulation. Everything's looking good.
Michigan - Foundation & Backfill
Michigan - Excavation
Excavation has begun at 394 Michigan! Here are some shots of the site on a really nice day.
Charlotte - Rough Framing
442 Charlotte is moving along quickly. We've been luck with minimal rain days. Our carpenters are working on the roof sheathing now. The next steps are shingles, concrete slabs in the basement & garage, then closing the house up with windows & exterior doors.
Hamilton - Tile & Stairs
Tile prep work has begun over at 1850 Hamilton. The tile flooring in the laundry room and 2nd floor furnace room have been installed. Custom oak stairs have been installed. The iron balusters will be put into place after painting and staining.
Hamilton- Insulation
1850 is Insulated. Drywall to being next week. I am very excited to get moving again on this home. There will be tons of great pictures coming up with all the decorative trim details going in. While we're waiting for the good stuff, here's some pictures of insulation & drywall setup.
Charlotte - Foundation
Construction has started for 442 N Charlotte. The excavation, footings, and foundation are done. This one is moving quick. We started the excavation in late February. And thankfully the weather has been working with our schedule.
Hamilton - Rough
Exterior is closing up and coming together. The Electrician is starting work and we should be ready for the rough inspections in a few weeks.