The first floor deck is on. We helped raise the back wall today. Hopefully Com Ed will hook up the electric soon so we can get off the generators.
Home Progress
111 S Bothwell - Foundation
The foundation is up.
Once the small strips of Styrofoam are removed you'll see a small brick ledge that allows us to go lower with the bricks. This is a nice detail as is hides much of the concrete foundation on the finished home.
248 S Hale - Cabinet Installation
I almost forgot I took these. Here are a few pictures of when George was installing the kitchen cabinets a few weeks ago.
111 S Bothwell - Sewer & Water Hook up
At least the water got hooked up. The sewer was an old clay pipe that will need to be replaced. We will do that just before backfilling the foundation.
248 S Hale - Painting
Wood floors have been completed and stained. They have been covered for protection. We have the painters in there for the next few weeks.
248 S Hale - Grading
Fuzzy just finished grading the lot.
248 S Hale - Exterior, Garage, & Base
248 S Hale - Oak Floors Installed
The floors & stairs are in. Sidewalk, front, & rear stoop are poured. Interior doors, trim, and base are being installed.
111 S Bothwell
Here is a rough front elevation for the spec house on Bothwell. Construction begins soon.
248 S Hale - After Drywall
Here are a few rooms of Hale just after the drywall was put up before taping.